I know I've been slacking on updating this. Bathroom is still a work in progress but it's all small details for the most part now. No pics, will get some up soon when I can.
-I am done with 99% of tile, thankfully. A bit of grouting still needs to be done but it shouldn't be too lengthy of a process. I have one small issue and it is along the very top of the shower between the last row of tile and the ceiling. The gap is big enough that grouting it would probably look ridiculous, but small enough (and uneven enough due to sloping walls in an old house) that cutting tile for it is no small task.
-All drywall is in, taped and mudded. Will be texturing the walls and painting hopefully this weekend.
-Baseboards need to be cut, painted, and installed.
-Toilet is in and working. Sink will be going in this weekend hopefully.